Design changes mean Middle East has world’s worst project delays

Reuters
Construction projects in the Gulf are often over budget and over deadline
  • Average construction overruns add over 80% to timelines, says report
  • Disputes claims increase costs by more than a third
  • Around $2.65trn worth of projects planned or under way in the Gulf 
  • Dynamic nature of projects means international contractors not put off

Construction projects in the Middle East are facing some of the longest delays of any region in the world, with average overruns adding more than 80 percent to timelines, and dispute claims increasing costs by more than a third.

Despite the prevalent availability of cash reserves in the region, due to the high oil price boosting government coffers, projects often start too early, when proper designs were not in place.

However, industry insiders were upbeat that, in spite of the challenges, global investors and contractors had not been put off bidding for projects in the region and that sentiment was still high.

London-headquartered consultancy firm HKA’s fifth annual CRUX Insight Report investigated 1,602 projects in 100 countries valued at more than $2 trillion.

As part of the report it looked at 380 projects in 12 Middle Eastern countries, with an average value of $1.74 billion. It found that, on average, project delays added 83.1 percent extra to the final timeline, and resulted in average claims of around $154 million, the highest of any region in the world on both counts.

“Having the cash or funds ready for the project is one thing, but having the processes, governance and delivery strategy in sync is another,” Haroon Niazi, partner and head of the Middle East at HKA, told AGBI.

Building a stadium for Qatar 2022. Picture: Reuters

“This notion that the sooner we get on site, the sooner we’ll be able to start making progress takes priority.”

Sachin Kerur, UAE-based managing partner for the Middle East at law firm Reed Smith, said he is not surprised that the CRUX report found the region had the highest delays and dispute claims in the world.

“This has been an issue afflicting the regional construction sector for many years. We see the same issues emerge year after year,” he said.

The CRUX report found that the majority of claims for delays in the Middle East are design-centric and stem from lower levels of maturity in the construction and engineering industry.

“The high-risk, low-margin contracting model rules in most parts of the Middle East,” the report concluded.

“I’m not saying the design always has to be complete, or at an advanced stage, because sometimes it just won’t be,” said Niazi.

“But it’s having that recognition and those processes and procedures in place, in case the design is not going to be ready or sufficiently ready to progress.”

He also cited one unnamed Gulf giga project investigated for the report, which he said had seen substantial design changes after the project had officially started. 

“Six or nine months into the project and there are numerous design changes, to the extent the contractor is getting issued new drawings. On one of them, where they ask for people to circle changes, the whole drawing is being circled and that is a big issue.” 

While the coronavirus pandemic did not halt construction work completely in the region, it did slow down new contract awards and highlighted issues within the sector.

“In many ways the conditions compounded problems that lie at the heart of the region’s industry,” Reed Smith’s Kerur said.

“Some of these endemic issues, such as poor procurement choices and inadequate planning, would have caused delays even before Covid-19 delay impacts were apparent.”

Cranes dominating the Dubai skyline in 2018. Picture: Reuters

Data from project tracker portal MEED Project found that around $2.65 trillion worth of projects were planned or underway in the Gulf as of the end of June this year.

However, Kuwait-based Kamco’s latest Q3 construction report found that the total value of contracts awarded in the Gulf in the first nine months of this year declined by 26.2 percent year-on-year to $53 billion. 

Saudi Arabia accounted for more than half of total projects awarded and bucked the regional trend, with the kingdom’s total value of contracts rising 14.9 percent year-on-year to $30.3bn over the period.

The CRUX report said cashflow and late approval of payments were also issues, but, unlike periods during the global financial crisis in 2009, non-payment was no longer a problem.

“I think we’re still seeing delayed payments for sure, but we’re not seeing the situation of just non-payment,” Niazi said.

“There are specific employers in the region who are behind on payments, and it’s going to be them who will struggle to attract talent in terms of contractors showing the readiness to bid for their project.

Despite the challenges in the region, Niazi said the dynamic and ambitious nature of projects in the region meant international investors and contractors were not put off.

“If we look across the region – UAE, Qatar, and Saudi in particular – we’re still seeing international contractors coming into the market,” he said. “Investors are still looking at it relatively positively.”

Work in progress in Saudi Arabia. Picture: Reuters

Top causes of claim or dispute in the Middle East

  1. Change in scope
  2. Design information was issued late
  3. Contract interpretation issues
  4. Design was incomplete
  5. Contract management and/or administration failure
  6. Approvals were late
  7. Access to site/workface was restricted and/or late
  8. Cashflow and payment issues
  9. Poor management of subcontractor/supplier
  10. Design was incorrect

Source: The CRUX Insight 2022 Report

Latest articles

UAE president Sheikh Mohamed bin Zayed Al Nahyan and Egypt's president Abdel Fattah El-Sisi attend the signing ceremony of appointing Modon Holding as developer of Ras El Hekma

ADQ unveils plans for Ras El Hekma Egyptian project

Abu Dhabi sovereign wealth fund ADQ has revealed the plans for the Ras El Hekma mega development, which is expected to contribute $25 billion annually to Egypt’s GDP and create 750,000 jobs both directly and indirectly. The sovereign fund has appointed Abu Dhabi-listed Modon Holding as the master developer for the 170 million sq m […]

Advertisement, Person, Clothing

Almarai Q3 2024 profit rises 17% amid revenue growth

Almarai, the Middle East’s largest dairy farm, said third-quarter 2024 net profit rose 17 percent to SAR570 million ($152 million), compared with SAR486 million a year ago. The profit growth was driven by a 9 percent year-on-year increase in revenue to SAR5.2 billion amid growth in all product categories across all geographies, except Egypt. Despite […]

Clothing, Footwear, Shoe

PIF explores raising stakes in Japanese gaming companies 

Saudi Arabia’s Public Investment Fund is exploring increasing its stakes in Japanese gaming companies to develop the kingdom as a global centre for gaming. “There are always opportunities,” Prince Faisal bin Bandar Al Saud, vice chairman of Savvy Games Group told Kyodo News, a Japanese news agency. PIF now owns 8.6 percent of Nintendo, after […]

The ambitious plans to increase Abu Dhabi's GDP include investing in and encouraging non-oil sectors such as manufacturing, healthcare and bioscience

Abu Dhabi to announce new 2045 strategy for GDP growth

Abu Dhabi will soon launch a new economic strategy aimed at tripling its GDP by 2045, sources told AGBI. The strategy, expected to be released by the end of the year, outlines a broad transformation that seeks to further diversify the emirate’s economy, significantly reduce its reliance on oil, and position Abu Dhabi as a […]