Big events take priority for stretched Saudi builders

Saudi construction delay Shutterstock
Despite a slowdown for some Saudi construction schemes, housing and infrastructure will remain top priorities, observers say
  • Delays in 2030 construction ‘inevitable’
  • Concentration on international events
  • Smaller projects under scrutiny

There will be delays in delivering Saudi Arabia’s massive construction pipeline in time for 2030, but projects directly linked to specific international events such as the Asian Winter Games in 2029 will take priority, industry players told AGBI at the Big5 conference in Riyadh last week.

About $1 trillion in giga-projects are under way across Saudi Arabia, ranging from dozens of high-end hotels along the Red Sea coast to Neom, a futuristic new mega-city planned in the kingdom’s north-western corner.

Sean Doherty, head of programme and project management in Riyadh for the consultancy JLL, said housing, infrastructure and other projects vital to accommodate more people and advance economic growth will remain top priorities.

The kingdom is slated to host several global events, chief among them the Asian Winter Games in 2029, the Expo in 2030, and the football World Cup in 2034. The kingdom will have to continue at full speed on the construction programmes for these ambitious international commitments. 

The Asian Winter Games will be hosted in a planned mountain resort by the name of Trojena, part of the larger Neom project.

“Trojena has got to be developed,” Doherty said. “The Expo is also going to be a big one.”



Riyadh, where the World Expo 2030 event will take place, needs about 100,000 new hotel rooms to cope with that and other global events, according to various estimates.

Doherty said there were “lots of challenges around that. The government is working towards all the big events. But we need more players to come to the market”.

In December the Saudi finance minister, Mohammed Al Jadaan, in an interview with Bloomberg, acknowledged for the first time that the government had decided to postpone certain projects’ deadlines for completion by three to five years, while plans for others would be “rationalised”.  

Al Jadaan said the delays would boost capacity in the Saudi construction industry, reduce supply chain bottlenecks and avoid excessive inflationary pressures on the economy.

The minister did not specify which developments would be delayed.

The construction industry in the kingdom is currently operating under the eight-year-old Vision 2030 roadmap, a multi-trillion dollar plan to diversify the Saudi economy and boost residents’ social and cultural well-being.

Expect Vision 2040

As that deadline approaches, the expectation is that the government will soon release something of a follow-up, a Vision 2040, said Jason Morris, the managing director of KEO’s project and construction management division.

“Everything was never going to be finished by 2030, so Vision 2040 is what happens next,” he said. 

Morris said last year in particular saw authorities increase scrutiny of many projects’ expected return on investment. While performances in and around Riyadh and Jeddah continue to look strong, the picture might be less obvious in smaller, secondary cities.

“I think that as opposed to a funding issue, there’s been a realisation that the investment that they’re making could be better spent,” Morris said. “So I think organisations have just slowed down while reassessing. I don’t think anything stopped.”

Regardless of likely construction delays, Morris said, Saudi Arabia’s construction programme remains “like nothing anybody has ever seen” and “the volume of work still coming into the market is unprecedented”.

Wael Darkazanli, chief operations officer of Atheel Contracting, which has its headquarters in Riyadh, said timelines may change depending on government policies and priorities, “but what we see is, even if some projects may be delayed and priorities may change, the big picture is that Saudi Arabia is booming and there are a lot of opportunities here”.

Latest articles

Saudi US China Amit Medha

Saudi Arabia willing to drop China for US tech alliance

Saudi Arabia will sever technology ties with China if the United States compels it to, the chief executive officer of Alat, an investment company backed by $100 billion in capital from the Public Investment Fund, has revealed. According to Bloomberg US officials have told their Saudi Arabian counterparts that they will have to decide between […]

Investors at the Dubai Financial Market. Drake & Scull was suspended from trading in 2018

Drake & Scull losses narrow before return to trading

Dubai contractor Drake & Scull International has trimmed its losses in the first quarter of this year as it nears the end of a drawn-out capital restructuring process. The Dubai-based utilities and infrastructure engineering company said in a press release accompanying disclosures to the Dubai Financial Market (DFM) that revenue jumped 55 percent year on […]

Gas Pump, Machine, Pump

Adnoc Distribution to expand as earnings rise

Adnoc Distribution plans to open 15 to 20 more fuelling stations in 2024 after opening eight in the UAE, Saudi Arabia and Egypt in the year so far. The expansion increased fuel and non-fuel sales, driving revenue up by over 9 percent year on year to AED8.7 billion ($2.4 billion) in the three months to […]

Patrick Pouyanné, CEO of TotalEnergies, said last month that he expects the first phase of the project to be completed in 2025

Iraq forges ahead with plans for first big solar plant

Iraq is proceeding with its first large-scale solar plant, which will be constructed by France’s TotalEnergies. The 1GW plant will be built in Basra, southern Iraq, as part of a $27 billion investment agreement for an integrated project that includes four oil, gas and renewables facilities. According to reports it will supply clean electricity equivalent […]