Dewa’s $300m power plant set for Q1 2023 completion

Wam
Dewa aims to produce 100% of desalinated water by a mix of clean energy and waste heat by 2030

State-owned Dubai Electricity and Water Authority (Dewa) has completed 93 percent of the 829 megawatts (MW) fourth phase of the AED 1.1 billion ($299.47 million) H-Station power plant in Al Aweer with investments.

This phase will increase Al Aweer power station complex’s total capacity to 2,825 MW under climate conditions of 50 degrees Celsius and 30 percent relative humidity, the UAE state-run WAM news agency said.

Key testing and commissioning operations started in Q4, 2022. The project is expected to be operational in Q1 2023.

Saeed Mohammed Al Tayer, managing director and CEO of Dewa, said that this plant is one of the authority’s key projects as part of its goal to address peak electricity demand in Dubai.

The project will add to Dewa’s current installed capacity of 14,317 MW of electricity.

Nasser Lootah, executive vice president of generation (power and water) division at Dewa, noted that the project’s work is progressing according to schedule, while maintaining the highest levels of health, safety, quality, and efficiency.

The project is being implemented by a consortium comprising Siemens Energy and Elsewedy Power. It includes supplying, installing, testing, and commissioning three Siemens gas turbines with a total capacity of 829 MW.

The plant includes installing sub-devices and equipment from major international companies, such as natural gas compressors from Germany’s MAN and a natural gas treatment station from Dutch company Petrogas, the statement said.

Latest articles

Saudi Arabia's minister of communications and IT Abdullah bin Amer Al-Swaha met with Groq CEO and founder Jonathan Ross in the US in July

Aramco partners with US startup Groq for AI data centre

Saudi Aramco’s digital arm is partnering with US semiconductor startup Groq to build the world’s largest artificial intelligence inferencing data centre.  Unlike regular data centres, which handle a range of computing tasks, an AI inferencing data centre is designed specifically to run AI models that make rapid predictions or decisions.  The facility will use Groq’s […]

A water taxi in Dubai's Business Bay, where off-plan real estate prices surged in 2023

Prices stabilise in Dubai’s off-plan market as supply grows

Prices for off-plan real estate in Dubai are stabilising following a spike in 2023 as developers bring more projects to the market. Property prices for off-plan purchases in areas such as Dubai Hills, Business Bay and Jumeirah Village Circle increased by as much as 30 percent in 2023 compared to the previous year. In August, […]

Agility Korek

Iraqi telecoms firm loses appeal against $1.5bn corruption award

A $1.5 billion decision against an Iraqi telecom operator and a prominent Iraqi businessman has been upheld by the International Court of Arbitration, part of the  International Chamber of Commerce (ICC). The arbitrators found that Korek Telecom and its chairman and top shareholder, Sirwan Saber Barzani, had “participated in a corrupt scheme” to defraud the […]

Saudi grocery retailer BinDawood to invest $390m in delivery hubs

BinDawood to invest $390m in delivery hubs

Saudi grocery retailer BinDawood Holding has announced plans to invest SAR1.5 billion ($390 million) in robotics and delivery hubs. CEO Ahmad BinDawood confirmed that the investment, with partners, would be made in the company’s automated “dark stores” and the infrastructure needed to run them. The stores, typically hubs for online shopping orders, will range from […]